What is project notification

Project notification is prepared under Act No. 100/2001 Coll., on environmental impact assessment (EIA). It is submitted by the notifier, i.e. the person who intends to carry out the project.

In practice this is most often the investor, operator, developer, municipality, or business entity preparing a new structure, technology, site extension, or change to an existing operation.

Good notification should clearly show the authority:

  • what is actually to be built or operated,
  • where the project will be located,
  • what its capacity will be,
  • what technology will be used,
  • what impacts can be expected,
  • what measures the investor proposes.

Notification is not a building permit, operating permit, or final EIA opinion. It is an entry document on the basis of which screening procedure or another phase of the EIA process is conducted.

When a business needs notification

Notification is addressed when the planned project falls within the regime of the EIA Act. Basic orientation is carried out according to Annex No. 1 to Act No. 100/2001 Coll.

Some projects are in Category I and are always assessed. Others are in Category II and the competent authority decides in screening procedure whether they will be assessed further.

A business should address the EIA question already at the start of preparation, especially for these types of projects:

  • waste management facilities,
  • recycling centres,
  • industrial operations,
  • warehouse and logistics sites,
  • paint shops and surface treatment,
  • combustion and energy sources,
  • agricultural operations,
  • mining and raw material processing,
  • larger transport projects,
  • significant changes to existing sites.

EIA may concern not only a completely new structure. It may also concern a change to an existing project, for example capacity increase, technology change, operation extension, addition of a new emission source, or change in waste management.

In practice: If it is uncertain whether the project falls under EIA, it is advisable to verify classification before project documentation is completed. EIA addressed late can significantly delay subsequent permitting.

What notification is not

Project notification is often confused with project documentation. That is a mistake.

Project documentation addresses the technical execution of the structure. Project notification addresses the impacts of the project on the environment and public health.

It may draw on the project, but it must translate the project into environmental context. For business projects the main areas are usually noise, air, transport, waste, water, dust, odour, accident risks, impact on residents, and links to surrounding operations.

Notification is also not the same as EIA documentation under Annex No. 4 to the Act. EIA documentation is a more detailed supporting document prepared only if the project must be assessed further.

What happens after notification is submitted

Notification is submitted to the competent authority. Depending on the type of project this is usually the regional authority or the Ministry of the Environment (MŽP).

The authority first checks whether the notification contains the required particulars. If it is in order, it publishes it in the EIA Information System and sends it to affected bodies and affected territorial self-governing units.

Municipalities, regions, affected bodies, and the public may then comment on the project. At this stage requirements often appear for additional supporting materials, for example a noise study, dispersion study, transport assessment, biological survey, hydrogeological assessment, or a more precise description of technology.

The outcome of screening procedure is either a conclusion that the project will be assessed further in the EIA process, or a decision that the project is not subject to further assessment.

Where to find similar projects

Documents relating to the EIA process are published in the EIA Information System. Notifications, conclusions of screening procedures, documentation, reviews, opinions, and other related documents can be found there.

For an investor this system is useful even before preparing their own project. It can be used to verify how similar operations were assessed, what supporting materials authorities required, and whether similar projects ended already in screening procedure or continued into the full EIA process.

However, it is not appropriate simply to copy text from another notification. Every project has a different location, capacity, transport connection, neighbouring development, noise conditions, immission situation, and links to further permitting.

What notification must practically contain

The outline of notification follows Annex No. 3 to Act No. 100/2001 Coll. For the operator, however, what matters most is that the document is not only formally structured according to the outline, but actually corresponds to the planned operation.

Notification must clearly describe the notifier, project location, capacity, technology, inputs, outputs, operating regime, and expected impacts.

Outputs mean especially emissions to air, noise, wastewater, waste, transport, dust, odour, light impacts, or accident risks. For production and industrial projects a description of raw materials, storage, energy, handling, operating hours, and links to the existing site is also usually important.

Good notification should also explain why the project is proposed at that particular location, how it relates to the zoning plan, where the nearest residential or other sensitive structures are, and what measures the investor proposes to reduce negative impacts.

What supporting materials to prepare

For initial assessment it is not always necessary to have a complete project. Without basic data, however, notification cannot be prepared to a high standard. The more precise the inputs, the lower the risk of supplementation during the procedure.

For larger or sensitive projects it is advisable to prepare in advance a noise study, dispersion study, transport assessment, biological survey, or hydrogeological assessment. They are not always mandatory, but for many projects they determine whether the notification will be sufficient for the authority.

What the authority looks at most closely

The authority does not assess the project in isolation. It looks at its location, capacity, technology, surrounding development, cumulative effects with other projects, and real operational impacts.

For industrial operations the key areas are usually emissions to air, noise, transport, waste, wastewater, and accident risks. For recycling centres dust, noise from crushers and screens, stockpiles, heavy goods transport, and waste management are often addressed. For warehouse and logistics sites transport, noise, and land take are usually decisive. For energy sources rated power, fuel, emissions, stack, noise, and operating regime are addressed.

Cumulative impacts are also very important. If there are several sources of noise, transport, or emissions in the locality, it is not enough to assess only the new operation itself without context.

Most common mistakes in practice

The most common mistake is an overly general notification. The document formally contains chapters according to Annex No. 3, but lacks specific data on capacity, transport, technology, emissions, operating hours, or measures. The authority then lacks sufficient supporting materials and the procedure becomes complicated.

A second common mistake is incorrect project classification. The investor assesses only the main structure but overlooks related technology, waste, storage, energy, or capacity increase.

For changes to existing operations it is often forgotten that EIA may address not only a new structure but also a change of operation, technology change, or output increase.

A problem is also inconsistency between notification and project documentation. If notification states different capacities, different transport, different exhaust locations, or a different operating regime than the project, doubts and requirements for explanation arise.

Notification, EIA, and JES

EIA is a separate process under Act No. 100/2001 Coll. At the same time it may link to further environmental requirements, especially in procedures where the unified environmental opinion (JES) is addressed.

In practice this means that notification should be prepared so that it helps not only in screening procedure but also in further permitting steps. Affected bodies may already in their comments on notification indicate what supporting materials they will need in later phases.

For the investor this is a useful signal. If the need for a noise study, dispersion study, transport assessment, or other supporting document becomes apparent in time, it can be addressed earlier, before a problem arises in a subsequent procedure.

How to tell whether notification is sufficient

For Category II projects the main question in screening procedure is whether the project may have a significant impact on the environment.

If the competent authority concludes that a significant impact cannot be expected, the procedure may end with a decision that the project will not be assessed further under the EIA Act.

If the authority concludes that the project may have significant impacts, the project will be assessed further. This is followed by EIA documentation, comments, review, possibly public hearing, and binding opinion.

Well-prepared notification can help explain the real scope of impacts and proposed measures. Weak notification, on the other hand, increases the risk of further assessment or extensive supplementation.

What you can send us for assessment

For initial assessment send a brief project description, site plan, capacities, technology, operating hours, transport balance, data on emissions, noise, waste, water, and information on whether it is a new operation or a change to an existing site.

If you already have project documentation, zoning information, nature protection body opinion, or an authority requirement, send these supporting materials as well.

We will verify whether the project may fall under Annex No. 1 to the EIA Act, whether notification will be needed, what studies it is advisable to prepare, and what risks may arise in screening procedure.

Brief summary

Project notification is the first expert document in the EIA process. It describes the planned project, its capacities, location, technology, inputs, outputs, and possible impacts on the environment and public health.

It does not permit construction. It enables the competent authority to decide whether the project will be assessed further, or whether screening procedure is sufficient.

For a business the most important thing is to prepare notification substantively and concretely. Capacities, transport, noise, air, waste, water, operating hours, cumulative effects with the surroundings, and proposed measures are essential.

Send us a project description, site plan, capacities, technology, and main operational data. We will propose whether project notification will be needed, what studies to prepare, and how to set up supporting materials so they are usable for EIA, JES, and subsequent permitting procedures.

Factual basis of the article

SourcePractical significance
Act No. 100/2001 Coll., on environmental impact assessment (EIA)Basic legal instrument for the EIA process. It regulates when projects are assessed, how notification is submitted, how screening procedure, documentation, review, and opinion proceed.
§ 6 of Act No. 100/2001 Coll.Regulates project notification. The notifier submits notification to the competent authority and notification has particulars according to Annex No. 3 to the Act.
Annex No. 1 to Act No. 100/2001 Coll.Contains projects for which it is necessary to verify whether they fall into Category I or II.
Annex No. 2 to Act No. 100/2001 Coll.Contains criteria for screening procedure, especially the nature of the project, location, and character of possible impacts.
Annex No. 3 to Act No. 100/2001 Coll.Sets the structure and content of project notification.
EIA Information SystemPublic portal where notifications, conclusions of screening procedures, documentation, reviews, opinions, and other project documents are published.
Act No. 148/2023 Coll., on the unified environmental opinion (JES)Important for linking EIA to further environmental requirements for projects permitted under the Building Act.
Nature protection body opinion under Act No. 114/1992 Coll.Important for verifying possible impact on European important sites or bird areas.
Noise study, dispersion study, transport assessment, biological or hydrogeological assessmentNot automatically mandatory in every case, but for many projects they determine the quality of notification and whether the authority will require further supplementation or more detailed assessment.

From the above sources it follows that project notification should not be merely a formal document completed according to the outline. It should be a practical and defensible description of the project and its impacts.

The more precise the inputs on capacity, location, technology, transport, noise, air, and operating regime, the better the procedure can be prepared and the risk of unnecessary supplementation reduced.